BUS 515 Homework Week 10
Flora’s Fabulous Fountains’ (FFF) top product is its Model A. Which of the following product structure trees for the Model A is true?
Use the following information:
Flora is preparing for her busy season and is building 2500 Model A fountains. Calculate the gross requirements for each component assuming that there is no beginning inventory.
Use the following information:
Component | Immediate Parent | Usage per Parent | ||||||
A | none | - | ||||||
B | A | 2 | ||||||
C | A | 1 | ||||||
D | A | 3 | ||||||
E | A | 2 | ||||||
F | B | 4 | ||||||
G | B | 2 | ||||||
H | D | 3 | ||||||
I | D | 2 | ||||||
J | E | 1 | ||||||
K | E | 5 | ||||||
L | E | 2 | ||||||
M | F | 3 | ||||||
N | F | 6 | ||||||
O | H | 2 | ||||||
P | K | 1 | ||||||
Q | K | 2 | ||||||
Put the answers down into the table (If answer is zero, please enter 0, do not leave any fields blank):
Calculate the minimum replenishment time to build 2500 Model A fountains given the following beginning inventories.
Use the following information:
Problem 22
Bill’s Bar & Grill is open seven nights a week. Business is busiest on Thursday when there is a concert in the park across the street. Bill wants a workforce schedule that allows each employee two consecutive days off each week. He believes that he needs four employees on Tuesday and Saturday; five employees on Monday, Wednesday and Friday; six employees on Thursday and Sunday. Employees #1 and #5 asked him to have one of their days off on Monday; employees #3, #4 and #6 asked for one of their days off on Tuesday, Sunday and Thursday respectively. Bill agreed. Develop a workforce schedule for Bill.